SpaceX Natural Gas Pipeline: 32.4 Miles Across Brevard by August 2027
The SpaceX natural gas pipeline proposed for Brevard County is 32.4 miles of 16-inch steel line with a projected in-service date of August 2027. Those figures come from filings at the Florida Public Service Commission, where a SpaceX subsidiary named Coastal Connect Services, LLC asked for approval to operate as a natural gas transmission company. Commission staff recommended approval on September 24, and the item was on the October 6 agenda.
The route is not set. The company told the state it is still being worked out around available rights of way.
What the SpaceX Natural Gas Filing Says
Coastal Connect Services filed its petition on June 8, 2026, in Docket No. 20260094-GU, and refiled it September 3 with confidential contract terms redacted. The company is a Texas limited liability company registered in Florida and, in its own words to the commission, a direct subsidiary of SpaceX.
The line would carry natural gas from the Florida Gas Transmission interstate pipeline to SpaceX's facilities at Cape Canaveral. The staff memo says SpaceX liquefies natural gas for rocket fuel. SpaceX would contract for all of the capacity. Coastal Connect would move the gas and never own it.
The details the company gave staff in its July 10 responses:
Length: an estimated 32.4 miles, starting and ending inside Brevard County.
Pipe: 16-inch steel transmission line, with a planned operating pressure of 1,480 to 2,140, subject to final design.
Tie-in: the Florida Gas Transmission line, about 1.5 miles east of the Indian River and southwest of State Road 528.
Meter station: within a few hundred feet of that tie-in.
In service: August 2027, depending on the commission, final engineering, right-of-way acquisition, environmental and local permitting, construction, and inspections.
Why SpaceX Wants Its Own Line
SpaceX trucks in all of the natural gas it uses at the Cape as liquefied natural gas. The filing puts it at hundreds of truckloads per launch and says the volume will rise with more launches and larger vehicles.
One gas line already reaches the spaceport. It belongs to Florida City Gas. Coastal Connect told staff that line is small, more than a mile from where SpaceX needs gas, and does not connect to the delivery points. SpaceX talked with Florida City Gas about an expansion and decided the terms, timing, and cost did not work.
Florida City Gas asked to intervene on August 28. It told the commission its investment in the spaceport area could be stranded and that it plans to expand there. Staff called the request premature, because a protest can only be filed after the commission issues an order.
For scale on the launch side: SpaceX is asking federal regulators for 76 Starship launches a year from Cape Canaveral.
Where the Approval Stands
Staff's September 24 memo recommended that the commission approve the tariff. It recommended no action on the SpaceX contract itself, because both companies filed the affidavits that make a negotiated rate valid under state law.
Trade coverage published October 8 reports that commissioners approved the tariff on October 6 as staff recommended. No written order had posted as of October 9, so treat the vote as reported until one does. Once it does, anyone whose interests are substantially affected has 21 days to protest.
The tariff is permission to operate as a transmission company. It is not a construction permit and it does not fix a route. Two more facts from the memo matter for what comes next. A line under 100 miles that stays in one county is exempt from Florida's pipeline siting certification. And because the line stays inside Florida under state rate regulation, the company says it falls outside Federal Energy Regulatory Commission jurisdiction.
RCRE Take
For Brevard landowners: 32.4 miles of pipe needs a continuous strip of easements or purchased right of way, and the company has said in writing that the route depends on what property is available.
For industrial tenants and buyers: August 2027 is the company's own date for gas service, and the filing lists the conditions it depends on. If your business plan depends on Starship launch volume, plan around that date as the earliest case. Buildings near the Cape that exist today are on our industrial and warehouse space for lease page.
For other gas users along the route: the tariff lets Coastal Connect serve other large-volume customers only if they have no gas service today and sit more than a mile from an existing utility main. All of the first capacity is committed to SpaceX.
If you own land in north or central Brevard and want to know what an easement request does to its value, call 321-514-0876 or look at current commercial land for sale in Brevard.
Frequently Asked Questions
Does the SpaceX natural gas pipeline need federal approval?
Not from the Federal Energy Regulatory Commission, according to the company. A pipeline that operates entirely inside one state with state-regulated rates is exempt under what is called the Hinshaw Amendment. Coastal Connect told the Florida commission it will need a federal operator identification number from the pipeline safety agency, PHMSA, before it operates the line.
Can other Brevard businesses connect to the pipeline?
Only under narrow terms. State law requires a transmission company to offer access when it has capacity, and Coastal Connect told the commission it expects none at the start because SpaceX has contracted for all of it. The tariff also limits new customers to those with no current gas service who are more than one mile from an existing utility gas main.

Sources
Florida Public Service Commission staff recommendation, Docket No. 20260094-GU, September 24, 2026: the staff recommendation, the October 6 agenda date, the filing and refiling dates, the 32.4-mile and 16-inch figures, the Florida City Gas motion, the one-mile tariff rule, the siting exemption, and the 21-day protest period. Read October 9, 2026.
Coastal Connect Services, LLC, responses to staff's first data request, filed July 10, 2026: the tie-in location, meter station, operating pressure, August 2027 in-service date and its conditions, the truckload statement, the SpaceX ownership statement, and the account of the Florida City Gas line. Read October 9, 2026.
Florida Public Service Commission staff memorandum on tariff suspension, July 23, 2026: the June 8 petition and the statement that SpaceX would contract for all capacity. Read October 9, 2026.
Tesla North, October 8, 2026: the report that the commission approved the tariff on October 6. No commission order was available to confirm it when this was written.
Written by Cassandra Hartford, founder and CEO of Reach Commercial Real Estate. She has worked in Brevard County commercial real estate for 17 years, representing buyers, sellers, landlords, and tenants across Florida's Space Coast.